Lead Times for Standard Distribution Products

(Posted  Jan. 31, 2012)  

Pin Type Insulators (Standard)

Low Voltage High Voltage
Cat. No. ANSI Lead Time Cat. No. ANSI Lead Time
5R 55-3 Stock 27R 56-1 2 weeks
VI 605R 55-3 4 weeks VI 627R 56-1 4 weeks
6R 55-4 3 weeks 133R 56-2 Stock
VI 606R 55-4 4 weeks VI 633R 56-2 Stock
8R 55-2 Stock 145R 56-3 Stock
9R 55-5 Stock VI 645R 56-3 8 weeks
VI 609R 55-5 12 weeks 255R 56-4 Stock
11R 55-6 Stock      
VI 611R 55-6 3 weeks      

Pin Type Insulators (Special Designs)

Fog Bowl High Leakage Distance
Cat. No. Neck/Pin Lead Time Cat. No. kV/Pin Lead Time
35 C/1 inch 3 weeks 33R 15/1 inch Stock
39R F/1 inch 1 week 34R 15/1 3/8 in. 5 weeks
40R F/1 3/8 inch Stock      
41R J/1 inch Stock      
42R J/1 3/8 inch 4 weeks      

Spool Insulators, Guy Strain Insulators

Spools Guy Strains
Cat. No. ANSI Lead Time Cat. No. ANSI Lead Time
VI 2611 53-1 Stock VI 4602 54-1 Stock
VI 2612 53-2 8 weeks VI 4604 54-2 Stock
VI 2613 53-3 10 weeks VI 4606 54-3 Stock
VI 2617 - Stock VI 4656 54-4 Stock
VI 2626 53-4 Stock

Line Post Insulators (Tie Top)

Distribution (Non ANSI) Type ANSI Type
Cat. No. kV/Neck Lead Time Cat. No. ANSI Lead Time
2115 13.2/F Stock 2025 57-1 Stock
2120 13.2/F Stock VI 57-1 57-1 10 weeks
2127 23/F Stock 62055 57-2 6 weeks
2130 13.2/C Stock VI 57-2 57-2 12 weeks
2135 13.2/C 12 weeks 62056 57-3 1 week
2137 23/C Stock

Line Post Insulators (Clamp Top)

Vertical Mounting Horizontal Mounting
Cat. No. ANSI Lead Time Cat. No. ANSI Lead Time
62150 - 7 weeks 62250 - 7 weeks
62153 57-11 7 weeks 62253 57-21 7 weeks
62155 57-12 5 weeks 62255 57-22 5 weeks
62156 57-13 2 weeks 62256 57-23 2 weeks
62157 57-14 5 weeks 62257 57-24 2 weeks
62158 57-15 12 weeks 62258 57-25 6 weeks
62159 57-16 12 weeks 62259 57-26 Stock

Line Post Insulators (Pole Gain Mounting)

Gain Mounting Gain Mounting
Cat. No. ANSI Lead Time Cat. No. ANSI Lead Time
62353 57-31 Stock 62357 57-34 4 weeks
62355 57-32 2 weeks 62358 57-35 6 weeks
62356 57-33 2 weeks 62359 57-36 6 weeks

Suspension Insulators

Polymer Insulators Porcelain Insulators
Cat. No. ANSI Lead Time Cat. No. ANSI Lead Time
8015 (EPDM) DS-15 2 weeks 804 52-1 Stock
8215 (Silicone) DS-15 Stock VI 52-1 52-1 Stock
8025 (EPDM) DS-28 Stock 817 52-9 Stock
8225 (Silicone) DS-28 2 weeks VI 52-9 52-9 6 weeks
8035 (EPDM) DS-35 2 weeks 820 - Stock
8235 (Silicone) DS-35 2 weeks 834 - Stock
      850 - 8 weeks
      VI 52-3 52-3 Stock
      VI 52-4 52-4 Stock

Pin Post Insulators

Low Voltage High Voltage
Cat. No. kV/Pin Lead Time Cat. No. kV/Pin Lead Time
144 14.4/1 inch Stock 147R 34.5/1 inch 1 week
43R 25/1 inch 2 weeks 148R 34.5/1 3/8 inch Stock

Lead times are for normal order quantities and are subject to prior sale. For small quantities or unusually large quantities please consult the factory or your local victor agent.