Lead Times for Station Posts, Indoor Insulators, and Special Porcelains

(Posted  Jan. 31, 2012)  

Low Voltage ANSI Standard Station Posts (7.5 - 69 kV)

Standard Strength High Strength
Cat. No. TR No. Lead Time Cat. No. TR No. Lead Time
1750 202 7 weeks 1766 222 3 weeks
1751 205 7 weeks 1767 225 8 weeks
1752 208 7 weeks 1768 227 8 weeks
1753 210 3 weeks 1763 231 8 weeks
1754 214 6 weeks 1764 267 8 weeks
1755 216 6 weeks 1765 278 6 weeks

High Voltage ANSI Standard Station Posts (115 - 230 kV)

Standard Strength High Strength
Cat. No. TR No. Lead Time Cat. No. TR No. Lead Time
1720 286 Stock 17PA25 287 Stock
1721 288 Stock 17PA26 289 10 weeks
17PA22 291 8 weeks 17PA27 295 8 weeks
17PA23 304 6 weeks 17PA28 308 8 weeks
17PA24 312 8 weeks 17PA29 316 8 weeks

High Voltage ANSI Standard Station Posts (345 - 500 kV)

10 weekCat. No. TR No. Lead Time Cat. No. TR No. Lead Time
16PT00 324 8 weeks 16PA11 371 8 weeks
16PT01 367 8 weeks 16PA12 372 8 weeks
16PT02 368 8 weeks 16PA13 373 8 weeks
16PT03 369 8 weeks 16PA20 379 8 weeks
16PA10 330 8 weeks 16PA30 391 8 weeks

Switch Insulators (OEM Type)

2 1/4 Inch Bolt Circle In - Line Switch Insulators
Cat. No. BIL Lead Time Cat. No. BIL Lead Time
1735 150 3 weeks 1740 95 1 weeks
1736 125 3 weeks 1741 110 10 weeks
1737 95 3 weeks 1742 150 4 weeks
1738 110 3 weeks 1743 200 8 weeks
1739 150 3 weeks 1744 250 1 week
      1745 350 8 weeks

Cap and Pin Replacement Insulators

Cat. No. Equiv. TR Lead Time
1746 10 6 weeks
1747 13 6 weeks
1748 7 6 weeks
Others Consult Factory

Indoor Bus Support Insulators

Cat. No. ANSI/kV Lead Time Cat. No. ANSI/kV Lead Time
5651 A-10/4.8 2 weeks 5850-33 A-30/4.8 Stock
5652 A-10/7.2 2 weeks 5851-35 A-30/7.2 1 week
5750 A-20/4.8 2 weeks 5852-33 A-30/13.2 Stock
5751 A-20/7.2 2 weeks 5853-32 A-30/14.4 1 week
5752 A-20/13.2 2 weeks 5854-33 A-30/23 3 weeks
5753 A-20/14.4 2 weeks 5855-35 A-30/34.5 6 weeks

Fuse Cut Out Porcelain

Cat. No. BIL/LD Lead Time
18444 95/8.5 6 weeks
18445 125/11 6 weeks
18560 150/17 6 weeks
18736 170/26 6 weeks

Lead Times are subject to prior sale. For unusually large quantities or for small quantities please contact the factory or your Victor agent for lead times.

For products not listed here, please consult the factory or your local Victor agent for lead times.